Piping inspection and supervision, explained from scratch

CertificationSign in

Try a material grade (A106), a standard (API 5L) or a term (hazardous area).

↑↓ navigate↵ openAll results & filters →

Piping

Preheat and post-weld heat treatment — hydrogen, hardness, and reading the chart

What preheat is actually for, why interpass temperature has a ceiling as well as a floor, when PWHT is required and when it may be exempted, how to read a chart recorder trace against the specified cycle, and the hardness survey that decides it in sour service.

AdvancedOil & GasPetrochemicalPharmaceutical

Standards referencedASME B31.3ASME Section IXNACE MR0175API 577

Two thermal cycles bracket a weld: one before it and one after. They are specified separately, for different reasons, and both are routinely treated as formalities by people who have not had to explain a cracked joint.

Preheat

What it is for

Not to make the metal easier to melt. To slow the cooling rate.

A thick cold section acts as a heat sink and pulls the heat out of a weld very quickly. Fast cooling does two bad things at once:

  • Hydrogen is trapped. Hydrogen dissolves into the molten pool from moisture, oil, rust or damp electrodes. Given time it diffuses out. Cooled fast, it stays — and hydrogen in a hard structure under residual stress is the recipe for delayed cracking, which can appear days after the weld looked perfect.
  • A hard, brittle structure forms in the heat-affected zone.

Preheat attacks both by slowing the cooling. Which is why it is specified by material and thickness — the two things that set the cooling rate — and not by how cold the morning feels.

Interpass temperature

Preheat has a minimum, maintained throughout. Interpass also has a maximum.

Measuring it

A pipe joint on a run at grade wrapped in ceramic heating mats and insulation blankets bound with wire, with a bundle of thermocouple wires emerging from under the wrapping and running across the ground to a portable circular chart recorder standing on a frame nearby. The recorder door is open, showing the paper chart and its inked trace. A unit and workers are out of focus behind at dusk.
The wrapping, the thermocouple bundle and the chart, which are the three parts of the evidence. What the chart is worth depends entirely on where the other end of those wires is attached.

Post-weld heat treatment

When it is required

Driven principally by thickness, with material group setting where the threshold falls. B31.3 states requirements and exemptions below stated thicknesses; carbon steel is exempt well above where the chrome-moly alloys have long since required it.

Service can add its own requirement on top — sour service being the obvious case.

What it does

Holding the joint at temperature lets residual stresses relax, tempers the hard structure left by rapid cooling, and drives off remaining hydrogen.

Reading the chart

The record is a trace, and there are four things on it, not one.

What to read Why
Heating rate Too fast and the outside expands against a cold core, creating its own stresses. The spec controls it
Soak temperature Within the specified band — and the band has a top as well as a bottom
Soak time By thickness, and it starts when the coolest monitored point reaches temperature
Cooling rate Controlled down to a stated temperature, then free

Reading only the peak and the hold time misses half of what the cycle was meant to control.

A temperature against time trace. The curve rises along a controlled heating ramp, holds through a soak band bounded by a minimum and a maximum, then falls along a controlled cooling ramp before being allowed to cool freely. Each of the four regions is annotated with what the specification controls there, and the thermocouple positions are marked on the soak section.
Read only the peak and the hold time and you have checked two of the four things the specification controls.

Thermocouples

The trace is evidence about the metal only if the sensors were on the metal, at the positions the procedure specified — including the coolest part of the assembly, which is what the soak time is counted from.

A beautiful chart from badly placed thermocouples records a cycle that part of the joint never experienced. Placement is part of the record, not a detail of the setup.

Hardness, and sour service

Where the service limits hardness — sour service above all, under NACE MR0175 and ISO 15156 — a hardness survey is the verification that the thermal cycles did their job.

Hardness is the practical proxy for susceptibility to sulphide stress cracking, and the heat-affected zone is where an uncontrolled cycle leaves a hard band. On those lines, preheat and PWHT stop being paperwork and become integrity items with a measurement attached.

See material degradation.

Welding to a spool that has already been treated

The auditable record

For PWHT: the chart trace, the thermocouple positions, the equipment and operator, the procedure, and — the one most often missing — the joints it covered, by weld number.

A chart that cannot be tied to specific welds proves a cycle happened somewhere. That is not the same as proving it happened to this joint, and at handover it is the difference between a closed line and an open question.

What to take away

  • Preheat slows cooling — against hydrogen cracking and a hard HAZ. Not to help melting.
  • Interpass has a maximum too, protecting toughness.
  • Measure preheat through the section, not beside the torch.
  • PWHT is driven by thickness and material group, with service on top.
  • It relaxes stress and tempers hardness — and repairs nothing.
  • Read the chart for ramp, soak band, soak time and cooling, not just the peak.
  • Thermocouple placement is part of the evidence; soak counts from the coolest point.
  • Hardness survey is the verification in sour service.
  • Welding to a treated spool undoes it locally — clamp instead.
  • Tie every chart to weld numbers.

Check your understanding

10 questions. Nothing is recorded — this is just for you.

1What is preheat principally there to achieve?
2Why does interpass temperature have a maximum as well as a minimum?
3Where should preheat be measured?
4What principally decides whether a carbon steel joint needs post-weld heat treatment?
5What is PWHT doing to the joint?
6A chart recorder trace shows the correct soak temperature and duration, but a very steep heating ramp. What is the concern?
7Why does thermocouple placement matter when reviewing a PWHT record?
8In sour service, what is the hardness survey establishing?
9A support shoe is to be welded to a line that has already been post-weld heat treated. What is the issue?
10What should be in the PWHT record for it to be auditable?

#piping#welding#inspection#qaqc#pwht#fabrication#b313